Project Overview

The Papua New Guinea Bougainville Province Hydrometallurgical Leaching Plant processes secondary copper-gold ore from the Panguna mine tailings. WSHT Mining Group designed a complete hydrometallurgical facility producing LME Grade A copper cathode with gold recovery from leach residues.

Ore Characteristics

The feed material is historical mine tailings containing 0.9% Cu (oxide) and 0.4 g/t Au. Copper occurs as chrysocolla, malachite, and minor chalcocite. Gold is fine-grained and associated with iron oxide gangue. The material is free-digging and requires minimal crushing.

Process Flow

Material Handling: Historical tailings are excavated by excavator and transported by 30-t rigid haul trucks to the agglomeration plant. No primary crushing required due to fine particle size of tailings feed.

Agglomeration & Heap Leach: Tailings are mixed with cement (20 kg/t) and sulfuric acid (5 kg/t) in a rotary drum agglomerator, then stacked on a 100 m × 80 m heap pad. Leach cycle: 60 days. PLS copper concentration: 4-6 g/L Cu.

SX-EW: PLS is processed through a 2-stage mixer-settler SX circuit (LIX 984N organic). Strip solution feeds a 200-cathode EW plant. Current density: 280 A/m². Cathode purity: 99.99% Cu (LME Grade A).

Gold Recovery: Spent heap leach residue is repulped and processed through a CIL circuit (4 tanks × 80 m³) for residual gold recovery. Gold recovery from residue: 45-50%.

Key Equipment

设备Specification产能
CAT 390F ExcavatorMaterial handling300 t/h
3× 30t Haul TrucksRigid frame, off-roadTransport
Rotary AgglomeratorΦ2.0×6 m, 50 t/hCement mixing
Heap Leach Pad100 m × 80 m, HDPE lined500 TPD
2-Stage SX CircuitMixer-settlers, LIX 984NCu extraction
200-Cell EW PlantStainless cathodesCopper cathode
4× CIL Tanks5.0 m dia × 4.5 m, 80 m³Gold from residue
Tailings Residue Dam50,000 m³, linedSpent residue

项目亮点

  • 产能: 500 TPD tailings processing
  • Copper Production: 6,000 TPA LME Grade A cathode
  • Gold Recovery: 45-50% from leach residue
  • Heap Area: 8,000 m² (expandable)
  • Acid Consumption: 25 kg/t (cement neutralization)
  • Power: 2.5 MW (diesel generators)
  • Timeline: 14 months EPC delivery
  • Location: Bougainville Province, PNG

项目亮点

高效交付

比计划提前30天完成,1,200多天的施工期间零安全事故。

超性能

工厂产能超过设计规格15%,在项目启动的前三个月内即可达到3,000吨/天。

环境合规

完全符合国际环保标准,包括ISO 14001认证。

客户满意度

5 年运维合同续签 —— 对我们交付质量和支持的有力证明。

是否有类似项目在考虑中?

我们的EPC团队已在全球交付了500多个采矿项目。请告诉我们您的项目情况——我们将在48小时内回复。

项目信息

  • 项目编号 WSHT-EPC-0335
  • 位置 巴布亚新几内亚的布干维尔
  • 矿物类型 项目案例研究
  • 完工年份 2025
  • 设计产能 500 tpd
  • 交付时间 14 个月
  • 设备数量 16 单位
  • 项目范围 全EPC + O&M⟦SEP⟧

EPC 项目热线

+86 135 2500 5907

今日与我们的资深EPC工程师交谈。免费咨询及现场评估。

启动您的EPC项目

从概念到投产 — 一个伙伴,一个承诺。

告诉我们您的矿体情况、目标产能和项目地点。我们的EPC团队将在48小时内提供定制提案。

EPC 热线 +86 135 2500 5907
项目邮箱 info@wshtmining.com